Case Studies

Recent Projects by Chico Electric.

City of Chico is having all the older generators replaced with new units which involves removal of the old generators, installation of new concrete pads, all new wiring and a new generator installed. Peterson Catapilar managed these projects and Chico Electric did the complete installations. Goal of this project was to back up the entire facility with a new generator tied to the main electrical panel

901 Fir Street

Crane lowering a yellow Caterpillar generator onto its concrete pad beside a building

Installation of new generator on new pad with new transfer swtich

 

New yellow Caterpillar standby generator on a concrete pad with workers nearby

Another job well done with the entire property now backed up with new Cat Generator

 

Fire Station #1

An older gas unit was removed and a new pad and Cat Generator installed in its place.

Yellow Caterpillar standby generator installed on a pad beside a red fence

New Generator installed and ready to run at Fire Station #1

 

City of Chico City Hall

Involved removal of an older unit and installation of new Cat Generator. Very complex project with conduits installed across building in first floor ceiling, underground across common walkway area and lifted into place into a very tight area.... very challenging and successful project.

Crane lifting a yellow Caterpillar generator over a wall while crew members watch

Bringing in the new unit over the wall and moving into place. The old generator is just in view in the right corner with the temporary generator in the back ground.

 

Yellow Caterpillar generator suspended from crane straps among trees during installation

Over the wall and a little closer to the pad

 

Yellow Caterpillar diesel generator installed on a concrete pad beside a brick wall

In place and ready to start testing and the final tie-in to the electrical system.

 

Landacorp

Lifetouch server room